ROAD CONSTRUCTION PROCEDURE BY RECYCLING MACHINE (Cont.#1) 5 15 Step 5 : Compact the stabilized area by the roller compactors to the required CBR Step 6 : Cure the Renolith base with water for 3-7 days Step 7 : The Renolith surface after completed Step 8 : Density test by sand replacement